The Village of Berwyn will be conducting snow removal and snow relocation operations over the coming days to address significant snow accumulation and improve roadway width, drainage, and safety (see the schedule below). To allow crews and contracted equipment to work efficiently, we ask all residents to remove vehicles from the listed streets on the scheduled days. Vehicles left on the roadway may limit our ability to complete the work.
Friday & Saturday – January 9 and 10
Snow removal and widening will take place on the following streets:
• 50 Street – from 52 Avenue to 49 Avenue
• 50 Avenue – from 52 Street to 49 Street
• 51 Avenue – from 52 Street to 50 Street
• 52 Street – from 52 Avenue to 48 Avenue
• 49 Avenue – from 52 Street to 49 Street
Monday – January 12
Snow removal and relocation will take place in the following streets/areas:
• 55 Avenue – from 50 Street to 52 Street
• 51 Street – from 55 Avenue to 54 Avenue
• Glenmeyer Park area
• 53 Street – from 55 Avenue to 54 Avenue
• Trailer Park area
Thank you in advance for removing vehicles from the listed streets on the scheduled days.